INLAND PIPE REHABILITATION-RFB-PWSA 2020-FOR, SMALL DIAMETER SEWER REHAB PROJECT


Project Specs:

Notice ID #: 6695

Bid Date: 01/19/2021

Type Of Notice: Sub-Bid Advertisement
Location: PA: Pittsburgh

BDOQ: DBE

Contact: See Notice Summary for details on how to respond to this notice.


Notice Summary:


INLAND PIPE REHABILITATION

IPRNE is requesting Subcontractor Quotes for the Pittsburgh, PA – PWSA 2020 Small Diameter Sewer Rehabilitation

This project bids on January 19, 2021

 

Please review the plans, specifications, and addenda by clicking the link below:

https://www.dropbox.com/sh/bqk172ai8tf0hko/AACycCVg1L-zVtA9zzBAYDGWa?dl=0

 

We are soliciting subcontractor work for the specified selected items and we have broken down the scopes into smaller tasks to make it economically feasible:

 

SCOPES:

Open Cut:

                Rock Obstruction Excavation – 10 CY

                Exploratory Excavation – 25 CY

                Hand Digging and Tunneling – 20 MHR

                Additional Bedding Material – 20 CY

                Concrete Encasement – 5 CY

                Flowable Fill – 10 CY

                Dewatering Pumping – 120 HR

                Miscellaneous Work Time for a Full Crew – 20 CHR

                Miscellaneous Premium Work for Full Time Crew – 8 CHR

                Master Plumber Time – 8 MHR

                Journeyman Plumber Time – 8 MHR

                CSX Protection Services – 8 Day

                CSX Construction Manager – 8 Day

                Erosion and Sediment Control – 1 LS

                Pipe installation:

PVC SDR 26

                              8” – 30 LF

                             10” – 10 LF

                             12” – 10 LF

                             15” – 190 LF

                             18” – 20 LF

                             20” – 10 LF

                             RCP Class IV

                             24” – 10 LF

                             30” – 10 LF

                             36” – 10 LF

                Sewer Laterals (4” – 10” PVC) – 50 LF

                Trench Excavation – 0 – 15’ – 1000 CY

                Additional Trench Excavation – 100 CY

                Aggregate Trench Backfill above Pipe Zone – 640 CY

                Earthen Backfill Above Pipe Zone – 80 CY

                Additional PVC Fittings – 10” and smaller – 10 EA

                Additional PVC Fittings – Larger than 10” – 10 EA

                Wye Installation on New Sewer Main up to 15” – 15 EA

                Wye Installation on New Sewer Main up to 15 and Larger” – 5 EA

                Connections into Existing Brick Sewer/Structure – 2 EA

                Removal of Shipping Braces from Existing Wye Connection – 10 EA

Precast Manhole Installation 0 – 15’ Depth:

                             48” – 22 EA

                             60” – 4 EA

                             72” – 1 EA

Precast Manholes over 15’ Depth:

                           48” – 20 VF

                          60” – 10 VF

                           72” – 5 VF

                Manhole Tie-in/Connection – 5 EA

                Invert Structural Repair – 5 CY

                Rigid Concrete Bulkhead 15” – 24” – 2 EA

                Flexible Bulkhead – 1 EA

                Blockstone Street Repaving – 10 SY

                Brickstone Street Repaving – 100 SY

                Brick Sidewalk (Re-Laid) – 10 SY

                Salvage and Deliver Blockstone and Brick – 50 SY

                Landscape Restoration – 500 SY

                Clearing and Grubbing – 250 SY

                Crushed Stone Sub-base – 190 CY

                Replace Manhole Casting with New Casting and/or Rasie Casting up 10 1-foot in Depth – 33 EA

                Raise Manhole to Grade, 48”, 1 – 4 FT Depth – 60 VF

                Raise Manhole to Grade, 48”, Greater than 4’ Depth – 20 VF

                Backfill Undermined Street – 20 CY

                Tree and Stump Removal – 1 EA

                Tree Removal and Replace – 1 EA

                Remove and Reset/Replace Fencing – 100 LF

Concrete Work

                Concrete Paving Base (All Classes) – 230 CY

                Concrete Sidewalk and ADA Handicapped Ramp – 100 SY

                Concrete Deep curb and Deep Radius Curb  - 80 LF

                Concrete Deck Curb and Deck Radius Curb – 80 LF

                12” x 6” Wedge Curb (Hand Placed) – 10 LF

Asphalt Work

                Cold Patch Bituminous Pavement Replacement – 180 TON

                Milling – Wearing Course – 2400 SY

                Milling – Binder Course – Primary Street – 1900 SY

                Milling – Binder Course – Secondary Street – 500 SY

                Bituminous Pavement Replacement – Wearing Course – 3000 SY

                Bituminous Pavement Replacement – Binder Course – Primary Street – 2570 SY

                Bituminous Pavement Replacement – Binder Course – Secondary Street – 650 SY

CCTV

                Pre TV/Cleaning (minimum 3 Passes):

                                8” – 1490 LF

                                10” – 290

                                12” – 2510 LF

                                15” – 27010 LF

                                18” – 6950 LF

                                20” – 730 LF

                                24” – 610 LF

                                30” – 700 LF

                                36” – 260 LF

Light Sewer Cleaning – 40 HR

                Heavy Sewer Cleaning – 200 HR

                Heavy Root and Deposit Removal – 50 HR

                Grinding of Protruding Sewer Lateral Connection – 160 EA

                Vacuum Truck – 8 HR

                Push Camera for Internal TV Inspection – 100 LF

                CCTV Inspection:

                8” – 15” – 100 LF

                16”- 24” – 40 LF

                25” – 36” – 20 LF

                Larger than 36” – 10 LF

Lateral

                Lateral Camera Inspection – 50 LF

Grouting

                Non-Structural Grouting for Pipe Joints – 80 GAL               

Bypass

                20” – 730 LF

                24” – 610 LF

                30” – 700 LF

                36” – 260 LF

Traffic Control

                Hourly Rate for Flagman

                Hourly Rate for Police Officer

                    

However, if you are able to quote other portions of this project, please do so. 

 

Quotes must be received by January 15, 2021

 

Forward to:

-         mbedford@teamipr.com – Meghan Bedford

-         Nrusch@teamipr.com – Nathan Rusch

 

IPRNE LLC is willing to review any responsible quote and will negotiate terms, if appropriate.  We will notify your firm if your bid is accepted for the project. 

IPRNE LLC will not be interested in joint venturing or partnering for this particular project.

The Subcontractor shall submit an itemized quality monthly invoice by the 25th of each month to ensure timely payment.

We encourage contracting with a consortium of DBEs when a contract is too large for a firm to handle individually.

 

 

IPRNE LLC is an Equal Opportunity Employer.

 

Thank you for your consideration.

 

Please feel free to call me if you have any questions or concerns. 

 


 Jennifer Elder  
Estimating Administrator

Inland Pipe Rehabilitation | Corporate
www.teamipr.com
: 404-927-4603

 

 



----- Advertising -----










Click Here

----- Advertising -----
Click Here
Click Here

Want To Advertise On This Page? Contact Us