ENTERPRISE CITY SCHOOLS-NCB-ENTERPRISE CITY SCHOOLS-FOR, MAINT BLDG & BUS SHOP PROJECT.
Notice Summary:
NOTICE FOR CONSTRUCTION BIDS
Enterprise City Schools – Maintenance Building & Bus Shop
In-Place Closure of Underground Storage Tanks & Installation of Aboveground Fuel Storage System
Proposed Construction Period: May 1 - July 31, 2025
Pre-Bid Meeting: December 10, 2024 10:00 am (CST)
Pre-Bid Meeting Location: 1648 East Park Avenue, Enterprise, Alabama 36330
Environmental Consultant & Project Manager: Environmental-Materials Consultants, Inc.
Project Summary: The Enterprise City School District is proposing to upgrade their current gasoline and diesel underground storage tank system into a new aboveground storage tank system. The project is to be performed during the 2025 summer break period when the existing fuel system can be shut down. The new AST system must be in full operation before the beginning of the new school year. Completion date is July 31, 2025.